Progress Report - Week of 4/17/2017
Our team worked really hard this past week to finalize the prototype and complete the final report. Testing of the prototype, as stated in the V&V paper, was completed and documented for future reference. This weekend, we will work on our final presentation.
Progress Report - Week of 4/10/2017
This week, we began working with the 3 Arduino Pro Micros instead of the Arduino Uno that we had been working with. There are still a few issues with the code that Daniel is working to fix. In the mean time, Christian and Nikki are working to complete all tasks that are independent of testing.
Progress Report - Week of 4/3/2017
We made a lot of progress this week. We have the system able to collect data from all three sensors. We are hoping to have the code finished by Saturday morning so we can continue our verification/validation testing. We are planning to meet on both Saturday and Sunday.